Completion of Delivery of all Equipment for CANCHAYLLO HPP July. 18, 2014

On July. 18, 2014 the last equipment and devices to be delivered for CANCHAYLLO HPP was transported to the Shanghai Port, China, from where the goods will be shipped to the Port Callao, Peru in about 40 days. The related shipments were adjusted correspondingly according to the revised schedule of the site civil construction work in matching the erection schedule at site in different stage. From now on all the parties in the project will do work harder to have the commissioning of the plant in coming 5 months after the last delivered equipment and devices were transported to site.